HANA connection to ECC DEV and ECC Sandbox Via SLT

Hi Experts,

 

In our current project due to time crunch, we are planning to connect HANA-DEV box to ECC-SANDBOX, with ECC-SANDBOX having all the data of ECC PROD, as the ECC DEV is not ready due to EHP upgrade.

 

My question is: If we are connecting HANA DEV to ECC Sandbox(With Same data as PROD) and then later connecting the same HANA DEV to ECC DEV(More or Less Data as Compared to PROD), then:

 

1. Is this practically possible, at all ?

 

2. If yes, what are the technical configurations /challenges which we should take into consideration ?

 

Looking forward to your fast response.

 

Many Thanks,

 

Regards,

Jatinder